Bord Pleanala's 4th deferral raises the big question 'WHY?'

category cork | environment | news report author Wednesday March 22, 2017 22:24author by CHASE - Cork Harbour Alliance for a Safe Environment.

Bord Pleanala have failed to meet their current deadline of 22 March for a decision on the Ringaskiddy incinerator application ( http://www.pleanala.ie/casenum/PA0045.htm ) and are to defer for a fourth time in order to request further information from the applicant, Indaver Ireland. No new date has been set.
smbabyfeeder.jpg

CHASE is infuriated by this latest extension and questions the credibility of a process that minimises time given to the community to thoroughly examine an application while granting extra time to the developer first to prepare the application and then to correct it.



CHASE spokesperson Mary O’Leary said “We have been fighting this proposal in one form or other since 2001. It is a torturous process and this is a real kick in the teeth. Indaver have been engaged with Bord Pleanala on this application since 30 August 2012, that’s over 4 and a half years ago. We are livid. Indaver have had every chance to get their homework right, they have failed to do so and they are still being spoonfed instead of being sent home. But the real question on everybodys lips is WHY?

Why are Bord Pleanala giving Indaver the opportunity to add further information at this stage, over a year after the application was submitted, 10 months after the oral hearing closed and 8 months after the statutory decision deadline of 12 July.

Why have Bord Pleanala not returned a decision when the Department of Defence stated categorically at the Oral Hearing ( http://chasecorkharbour.com/indaver-facility-will-carry...eded/ ) that the facility would have strategic implications for the Irish State, that it would “create a flight safety hazard to Irish Air Corps helicopter operations” and that risk control measures would need to be implemented which would “impact on the Irish Air Corps’ ability to operate helicopters into Haulbowline”.

Why have Bord Pleanala not returned a decision when the final day exposed false dioxin figures ( http://chasecorkharbour.com/serious-dioxin-figure-irreg...lose/ ) in Indavers application so serious that the Inspector was forced to break and take legal advice.

Why, when there are clear grounds for a refusal, but not for a grant of permission, has the Bord failed to make a call.”

CHASE steering committee will be meeting later this week to discuss the implications of this latest delay.

Related Link: http://chasecorkharbour.com/bord-pleanalas-4th-deferral-raises-the-big-question-why/